Fuel removal from Fukushima reactor may be delayed

20180629_14_520466_L.jpg
June 29, 2018
The operator of the damaged Fukushima Daiichi nuclear power plant says work to remove spent nuclear fuel from a cooling pool at one of its reactors may be delayed.
A total of 566 fuel units remain in the cooling pool at the No.3 reactor, which suffered a meltdown in 2011. Tokyo Electric Power Company, or TEPCO, planned to start removing the fuel as early as this autumn, as part of the decommissioning of the nuclear complex.
But on Thursday, TEPCO revealed the control board of a crane used in the removal malfunctioned during a test run last month. It blamed a voltage error and said the board will be replaced.
The company said the test run may be delayed by one or 2 months, pushing back the start date for fuel removal.
TEPCO’s chief decommissioning officer, Akira Ono, says he takes the glitch seriously as it shows key equipment was not handled properly.
He says that although safety must come first, his team still aims to stick to the original timetable and start the removal of nuclear fuel by around the middle of the current fiscal year, which ends in March next year.
Advertisements

3 thoughts on “Fuel removal from Fukushima reactor may be delayed

  1. Do you know if these MOX spent fuel assemblies are going into dry cask storage or into another spent fuel pool?

    Like

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s