The rod-like probe outfitted with a tong-like pinching device that was used to touch melted nuclear fuel debris at the bottom of the No. 2 reactor at the Fukushima No. 1 nuclear plant
February 18, 2019
A specially designed, remotely controlled probe touched melted nuclear fuel debris at the bottom of a ruined reactor at the Fukushima No. 1 nuclear power plant in the first successful operation to inspect radioactive debris through direct contact.
The plant’s operator, Tokyo Electric Power Co. (TEPCO), lowered the rod-like probe outfitted with a tong-like pinching device into the primary containment vessel of the No. 2 reactor at the crippled plant and used the machine to successfully lift pieces of the debris several centimeters.
The removal of the fuel debris is the biggest challenge in the long process of decommissioning the reactors, which will take at least three to four decades. The lifting of debris is a ray of hope in the grim battle to overcome the formidable challenge.
But the success was tempered by the fact that there were large chunks with slick surfaces the robot’s pinchers were unable to grab. The probe found that deposits in various conditions lie scattered about the bottom of the vessel. Some pieces are apparently entangled in the surrounding equipment.
Tasks in and around the No. 1 to No. 3 reactors at the nuclear plant cannot be carried out by humans because of dangerously high radiation levels. Nuclear fuel in the core of these reactors overheated and melted down after towering tsunami triggered by an epic earthquake knocked out vital cooling systems on March 11, 2011.
Read more: