Fukushima plant reactor #3 gets new roof cover

 

 
Workers at the crippled Fukushima Daiichi nuclear power plant have finished installing a new roof covering for the No.3 reactor building.
The work started last August to set up a dome-shaped cover. It is part of preparations for removing nuclear fuel from the reactor’s storage pool. A total of 566 spent and unused fuel units remain in the storage pool of the No. 3 reactor.
On Wednesday, workers installed the last part of the cover, which is 17 meters high and 22 meters wide, and weighs 55 tons.
The cover will prevent radioactive materials from spreading, and shield the building from winds.
Reactors at the Fukushima plant suffered meltdowns after a quake-triggered tsunami hit the plant on March 11th, 2011. The fuel units left in storage pools need to be removed as part of decommission work at the plant.
The plant’s operator, Tokyo Electric Power Company, will clear the pool of rubble and provide workers with training on remotely handling devices for the fuel removal.
Then, it plans to start removing nuclear fuel units from the No.3 reactor’s storage pool in autumn this year, ahead of those of other damaged reactors.
21 feb 2018 reactor 3 roof.jpg

 

Advertisements

Inside a meltdown-hit Fukushima reactor building

February 17, 2018
Seven years on, Tepco aims to pull fuel out of Unit 3’s rubble-strewn pool
1.jpg
A crane and dome-shaped roof have been erected on the top floor of Fukushima Daiichi’s No. 3 building, in preparation for removing rods and rubble from the spent fuel pool
 
FUKUSHIMA, Japan — As the Fukushima Daiichi nuclear disaster unfolded in March 2011, a hydrogen explosion ripped through the No. 3 reactor unit. Nearly seven years on, steel framing and other debris still litter the spent fuel pool, along with 566 fuel rods.
The painstaking process of removing the rods is expected to begin sometime in the fiscal year that starts in April. The fuel extraction will be a first for reactor Nos. 1-3 at the Tokyo Electric Power Co. Holdings facility, which was crippled by the earthquake and tsunami that hit northeastern Japan.
On Feb. 8, reporters from The Nikkei were allowed into the No. 3 building to get a sense of the work that awaits. 
A 20-minute bus ride from the town of Tomioka took us to Fukushima Daiichi. After donning masks and protective clothing, we walked toward Unit 3. An elevator slowly lifted us to the top floor of the building, about 36 meters up. There, a crane for moving the spent rods stood ready, wrapped in plastic sheeting. We peered down into the pool but could not see the fuel, which lies under 4 to 5 meters of water.
Large slabs of rubble that fell into the pool have been removed, but smaller pieces remain.
Other decontamination work is proceeding gradually. Radiation on the top floor was measured as high as 2,000 millisieverts per hour in the disaster’s immediate aftermath, but now it is less than 1 millisievert.
Still, caution is a must. Near the pool, our dosimeters displayed relatively high readings of up to 0.7 of a millisievert per hour. “The reading has climbed, so let’s leave for now,” a Tepco supervisor said. As we moved on, we frequently checked to ensure our exposure would not exceed 0.1 of a millisievert a day. 
 
Spent fuel has been removed from reactor No. 4, which was not operating when the tsunami hit the plant. But the job will be a challenge at the meltdown-stricken Unit 3. The rods and rubble will be extracted with heavy equipment operated remotely, from a separate administrative building. 
While it normally takes about two weeks to remove spent fuel, Tepco intends to proceed carefully over the course of two years.

Drone to probe Fukushima N-plant interior

February 10, 2018
feb 10 2018 drone inspection of reactor 3.jpg
Tokyo Electric Power Company Holdings Inc. plans to use a small unmanned aerial vehicle to closely inspect conditions inside the No. 3 reactor building of the Fukushima No. 1 nuclear power plant as early as this month.
TEPCO will use the drone to examine the location of scattered debris and the level of radiation inside the reactor building, among other things.
It will be the first drone-based research conducted inside the plant’s Nos. 1, 2 and 3 reactor buildings, in which nuclear meltdowns occurred.
The drone, called Riser, was developed by a British company. It measures 83 centimeters by 93 centimeters and weighs about four kilograms.
Riser is equipped with cameras and a dosimeter that can measure up to 2.5 sieverts of radiation per hour.
Even in indoor spaces inaccessible to GPS signals, the drone is capable of determining its position and avoiding obstacles using lasers.
The same model was used for decommissioning work at the Sellafield nuclear facility in Britain.
TEPCO’s plan is for the drone to enter the No. 3 reactor building through a bay for large cargo on the first floor, then fly upward through a series of openings from the first to the fifth floor.
The drone will check areas including the building’s third floor, which has not been sufficiently monitored because radiation levels are too high.
According to TEPCO, key equipment such as that used to cool spent nuclear fuel pools are located on the third floor.
Confirming the location of possible obstacles and the level of radiation is necessary before decommissioning work can progress.
Riser also has a mapping function that enables it to produce three-dimensional graphic images of its surroundings using lasers.
Combining these images with measurements of radiation levels allows for the production of maps outlining contamination levels inside the reactor buildings. TEPCO will consider making this kind of distribution map in the future.
A hydrogen explosion inside the No. 3 reactor building on March 14, 2011, destroyed the building’s upper structures.
Work is currently under way to construct a dome-shaped roof over the building to facilitate the removal of fuel that remains in the spent fuel storage pools.

Installation of a dome-shaped rooftop cover near completion at Unit 3 reactor

31 jan 2018 reactor 3.jpg
Japan Fukushima Cleanup
In this Thursday, Jan. 25, 2018 photo, an installation of a dome-shaped rooftop cover housing key equipment is near completion at Unit 3 reactor of the Fukushima Dai-ichi nuclear power plant ahead of a fuel removal from its storage pool in Okuma, Fukushima Prefecture, northeast Japan, during an exclusive visit by The Associated Press. The hardest-hit reactor at the Fukushima plant in the March 2011 disaster is moving ahead of the other two melted reactors seven years later in what will be a decades-long cleanup. (AP Photo/Mari Yamaguchi)

Worst-hit reactor at Fukushima may be easiest to clean up

By MARI YAMAGUCHI
jan 25 2018 reactor 3 dome.jpg
In this Thursday, Jan. 25, 2018, photo, an installation of a dome-shaped rooftop cover housing key equipment is near completion at Unit 3 reactor of the Fukushima Dai-ich nuclear power plant ahead of a fuel removal from… (AP Photo/Mari Yamaguchi)
OKUMA, Japan (AP) — High atop Fukushima’s most damaged nuclear reactor, the final pieces of a jelly-roll shaped cover are being put in place to seal in highly radioactive dust.
Blown apart by a hydrogen explosion in 2011 after an earthquake and tsunami hit Japan’s Fukushima Dai-ichi plant, reactor Unit 3 is undergoing painstaking construction ahead of a milestone that is the first step toward dismantling the plant.
 
The operating floor — from where new fuel rods used to be lowered into the core — has been rebuilt and if all goes as planned, huge cranes will begin removing 566 sets of still-radioactive fuel rods from a storage pool just below it later this year.
 
It has taken seven years just to get this far, but now the real work of cleaning up the Tokyo Electric Power Co. plant can begin.
“If you compare it with mountain climbing, we’ve only been preparing to climb. Now, we finally get to actually start climbing,” said Daisuke Hirose, an official at the plant’s decommissioning and decontamination unit.
Cleaning up the plant’s three reactors that had at least partial meltdowns after the earthquake and tsunami is a monumental task expected to take three to four decades. Taking out the stored fuel rods is only a preliminary step and just removing the ones in Unit 3 is expected to take a year.
Still ahead is the uncharted challenge of removing an estimated 800 tons of melted fuel and debris inside the cracked containment chambers — six times that of the 1979 Three Mile Island accident.
The area in and outside of Unit 3 is part construction site and part disaster zone still requiring protection from radiation. A makeshift elevator, then a wind-swept outdoor staircase, takes visitors to the operating floor, more than 30 meters (100 feet) above ground.
Daylight streams in through the unfinished section of the new cover, a tunnel-like structure sealed at both ends to contain radiation. An overhead crane that moves on rails stands at the side of the storage pool, the maker’s name, “Toshiba,” emblazoned in large red letters.
The explosion left major chunks of debris that have been removed from the storage pool, a painstaking operation done using remote-controlled machinery and with utmost care to avoid damaging the fuel rods. Smaller rubble lines the pool’s edge. The water’s surface is obscured by a blue netting to prevent more debris from accidentally tumbling in.
The severe damage to Unit 3 has, in the end, made it easier to clean up than the other two reactors.
Under the latest government roadmap approved last September, removal of the fuel rods from units 1 and 2 was delayed by three years until 2023, a second postponement from the original 2015, because further decontamination and additional safety measures are needed.
Unit 1 fell behind because of a delay in removing debris and repairing key components on the operating floor. The Unit 2 building remained intact, keeping high radiation and humidity inside, which makes it more difficult for workers to approach and decontaminate.
Radioactivity on the Unit 3 operating floor has fallen to a level that allows workers in hazmat suits and filter-masks to stay up to two hours at a time, though most work still needs to be done remotely.
The segments of the new cover were pre-assembled and are being installed one by one by remote-controlled cranes. With two pieces left, the plant operator says the cover will be completed in February.
Removing the fuel rods in Unit 3 will be done with a fuel-handling crane. It will move the rods out of their storage racks and pack them in a protective canister underwater. A second Toshiba crane, a 10-meter (33-foot) -high yellow structure across the operating floor, will lift the canister out of the pool and load it onto a vehicle for transport to another storage pool at the plant.
Crane operators and others assigned to the project, which requires caution and skill, have been rehearsing the procedures.
The 1,573 sets of fuel rods stored in spent fuel pools at the three reactors are considered among the highest risks in the event of another major earthquake. Loss of water from sloshing, structural damage or a power outage could cause meltdowns and massive radiation leaks because the pools are uncovered.
Hirose said that starting fuel removal at Unit 3 would be “a major turning point.”
Still, after the intact fuel rods are gone comes by far the most difficult part of decommissioning the plant: removing the melted fuel and debris from inside the reactors. Obtaining exact locations and other details of the melted fuel are crucial to determining the retrieval methods and developing the right kind of technology and robots. With most melted fuel believed to have fallen to the bottom, experts are proposing that it be accessed from the side of the containment vessel, not from the top as originally had been planned, based on the cleanup after an accident at the Three Mile Island nuclear plant in the United States.
Computer simulations and limited internal probes have shown that the melted fuel presumably poured out of the core, falling to the bottom of the primary containment vessels. Robotic probes at the Unit 3 and 2 reactors have captured images of large amounts of melted fuel, but attempts so far at Unit 1 have been unsuccessful.
Despite scarce data from inside the reactors, the roadmap says the methods for melted fuel removal are to be finalized in 2019, with actual retrieval at one of the three reactors in 2021. Hirose says it is premature to say whether Unit 3 will be the first.

Fukushima dome roof takes shape, but radiation remains high

4 dec 2017 dome roof n3.jpg
Construction continues on a domed roof on top of the No. 3 reactor building at the Fukushima No. 1 nuclear power plant.
High radiation levels are still limiting recovery work at the Fukushima No. 1 nuclear plant, a stark reality that reporters saw firsthand when they observed efforts to remove risk factors there.
Media representatives were invited into the plant in early December to see construction work, with the building of a domed roof over the No. 3 reactor building as the main focus.
4 dec 2017 dome roof n3 3.jpg
However, they were only allowed to stay on top of the roof for 20 minutes due to high radiation levels.
The roof is being put together directly above the storage pool for spent fuel. The dome is designed to prevent the spewing of radioactive materials when the fuel is actually removed from the pool.
The original roof of the No. 3 reactor building was severely damaged by a hydrogen explosion in the days following the March 11, 2011, Great East Japan Earthquake and tsunami, which led to the crippling of the Fukushima No. 1 plant.
4 dec 2017 dome roof n3 4.jpg
Spent fuel still remains in the storage pools located on the top floors of the No. 1 to No. 3 reactor buildings.
Plans call for removing the spent fuel first from the No. 3 reactor building.
Although the dome will help prevent the spread of radioactive materials, building parts and other debris as well as some equipment have still not been completely removed from the storage pool, which holds 566 fuel rods.
The collapsed roof and walls were removed to allow for the construction of the domed roof, which began in the summer. The domed roof is about 17 meters high, and a crane was also installed under it in November.
4 dec 2017 dome roof n3 2.jpg
Plans call for the removal of the spent fuel from the No. 3 building to begin in the middle of the next fiscal year.
Internal radiation exposure levels were measured before media representatives headed to the No. 3 reactor building. They were also required to don protective clothing as well as a partial face mask covering the mouth and nose from about 100 meters from the building.
Radiation levels close to the building were 0.1 millisieverts per hour.
An elevator installed into the scaffolding next to the reactor building took the media representatives to the roof, which had been covered with metal plates.
The so-called operating floor looked like any other newly constructed building roof, a sharp contrast to the twisted metal parts that covered the building shortly after the nuclear accident.
Tokyo Electric Power Co., the plant’s operator, captured video footage from within the reactors for the first time in July. Debris that appears to be melted nuclear fuel was found in various parts of the containment vessel.
To the south of the No. 3 reactor building stands the No. 4 reactor building, from where all the spent nuclear fuel has been removed.
To the north is the No. 2 reactor building, which avoided a hydrogen explosion. Beyond the building, cranes and other large equipment are working in preparation for the removal of debris from the No. 1 reactor building.
TEPCO officials cautioned media representatives about standing too long right next to the storage pool, which could be seen located about six meters below the roof. Debris was found within the pool while insulating material floated on the pool surface.
The radiation level near the pool was 0.68 millisieverts per hour. While that was a major improvement from the 800 millisieverts per hour recorded in the immediate aftermath of the nuclear accident close to seven years ago, it was still too high to allow for a stay of longer than 20 minutes.

Image shows extent of damage to reactor at Fukushima plant

1 dec 2017 corroded tubes reactor 3.jpg
Severely damaged parts of a device once used to move control rods are stuck in a hole inside the pressure vessel of the No. 3 reactor at the Fukushima No. 1 nuclear plant. (Provided by International Research Institute for Nuclear Decommissioning)
An image taken by an underwater robot shows corroded tubes stuck in a hole created by melted fuel in the pressure vessel of the No. 3 reactor at the Fukushima No. 1 nuclear plant.
The image offers clues on the extent of the damage caused when fuel rods in the reactor melted through the bottom of the pressure vessel after the disaster at the nuclear plant unfolded in March 2011.
Tokyo Electric Power Co., operator of the plant, sent the specially designed robot into the reactor in July. The company earlier released images taken by the robot that showed ‘what is believed‘ to be melted nuclear fuel debris.
In the image released on Nov. 30, TEPCO identified the severely corroded and damaged tubes as parts of a device used to move control rods. Normally, that device is located inside the pressure vessel.
TEPCO on Nov. 30 also said it would conduct another study inside of the containment vessel of the No. 2 reactor at the plant in January. The containment vessel surrounds the pressure vessel.
A telescopic stick more than 10 meters long and equipped with a camera will be used for the survey.